MediumWater Utilities

Copeland Square Sanitary Sewer Improvements change order

The Copeland Square sewer project wrapped up, but crews hit an unexpected storm pipe conflict that added $36,615 and new junction boxes. Final cost: $796,236.

1 mention (1 this month)Last discussed Oct 27, 2026
MediumWater Utilities

SPX Aids to Navigation equipment contract

The airport tower, which currently has no radar, will get ADS-B technology letting controllers track aircraft electronically. Costs are split with the airport's FBO, and federal reimbursement is possible.

2 mentions (1 this month)Last discussed Oct 27, 2026
MediumWater Utilities

Digester rehabilitation schedule extension

The Hilliard N. Fletcher plant rehab got 120 more days at no extra cost so the biological treatment process in two digesters can stabilize before the third digester is rehabilitated.

1 mention (1 this month)Last discussed Oct 27, 2026
MediumWater Utilities↑Rising

Nucor Sewer Line cleaning and assessment

A $161,725 contract with Suncoast Infrastructure was up for tentative award to clean and assess sewer lines in the Nucor area. It's routine sewer maintenance that helps prevent backups and failures.

4 mentions (3 this month)Last discussed Oct 27, 2026
LowWater Utilities

Bulk water treatment chemicals bid

The council was to rescind an earlier bid award and give the rest of the contract for bulk water treatment chemicals to the second-lowest bidder.

2 mentions (2 this month)Last discussed Oct 20, 2026
MediumWater Utilities

Water and sewer budget amendment

An amendment to the water and sewer exhibits in section 19-42 of the code was scheduled for introduction — this governs how water and sewer charges are structured.

2 mentions (1 this month)Last discussed Oct 20, 2026
MediumWater Utilities

WRRF check valve installation

A small but critical repair: a new check valve at the raw sewage pump station keeps sewage flowing the right way at the treatment plant.

1 mention (1 this month)Last discussed Oct 20, 2026
MediumWater Utilities

Water and Sewer Fund budget revision no. 1

An amendment to the fiscal 2027 water and sewer fund budget was up for introduction, possibly same-night adoption — affecting utility ratepayers' fund priorities.

3 mentions (2 this month)Last discussed Oct 20, 2026
HighWater Utilities

Intermediate wastewater treatment trial at Lift Stations 2 and 33

The city is spending big to keep sewer lift stations running — a $384,000 valve replacement closeout and a new three-year, $415,000-a-year chemical treatment contract. These stations move wastewater across town, so failures mean backups.

2 mentions (1 this month)Last discussed Oct 6, 2026
HighWater Utilities

Lift Station 22 Force Main Replacement

The council was scheduled to tentatively award a roughly $1.6 million contract to REV Constructions, Inc. to replace the Lift Station 22 force main — key sewer infrastructure. No record shows whether the award was made.

4 mentions (1 this month)Last discussed Oct 6, 2026
LowWater Utilities

Reservoir and creek monitoring

A $13,575 joint funding agreement with the U.S. Geological Survey would keep a stream aging station operating on Cribbs Mill Creek, supporting water quality data.

2 mentions (1 this month)Last discussed Oct 6, 2026
MediumWater Utilities

Lift Station 3 parking lot lighting repair

The parking lot near the Lampigator train trestle lost power service early last month. The city is paying Premier Service Company $12,405.35 to fix it, funded through facility renewal.

1 mentionLast discussed Sep 29, 2026
MediumWater Utilities

Mercedes sewer force main expansion

Phase 3 of the Mercedes Force Main is a $1.75 million sewer capacity project awaiting final state sign-off before construction starts late this year.

1 mentionLast discussed Sep 22, 2026
LowWater Utilities

Water Distribution System Engineering Standards Manual

New 2026 engineering standards now govern how the city builds and maintains its water pipes — better consistency for developers and utilities staff.

1 mentionLast discussed Sep 22, 2026
MediumWater Utilities

Subdivision infrastructure acceptance — Cloverdale at Hackberry and Bryant at 15th

The city was set to take over maintenance of completed streets and infrastructure in Highgrove Phase 4 and the sanitary sewer lines in Tartan Cove Phases 1, 2, and 6 — a routine but lasting commitment of public maintenance.

3 mentionsLast discussed Sep 1, 2026
HighWater Utilities

Water and sewer maintenance contracts

Contracts with Thornton, Musso and Bellemin for work at the Ed Love Water Treatment Plant ($17,127.20) and Lift Stations 2 and 33 ($12,705), plus public works contracts with Daikin, Edko and Cummins, were scheduled for approval.

6 mentionsLast discussed Sep 1, 2026
MediumWater Utilities

Northern Sewer Expansion Project Phase II

The city took over sewer lines for two new subdivisions and is securing appraisals on 29 tracts for the Northern Sewer Expansion Phase II — keeping capacity ahead of growth.

1 mentionLast discussed Sep 1, 2026
MediumWater Utilities

Academy Drive drainage improvements

The city plans to install benches on lots it bought on Academy Drive, spending $10,000 from the District 3 Improvements Fund. This is a neighborhood improvement for that district.

3 mentionsLast discussed Sep 1, 2026
MediumWater Utilities

Drainage improvement easements — Eastover and Cypress Point

Several drainage-related items were scheduled: a change order on the waterfall roadway drainage project, an engineering contract for 10th Avenue at 19th Street, and Lincoln Park drainage improvements. Flooding and stormwater concerns in these areas would be addressed if approved.

3 mentionsLast discussed Aug 18, 2026
MediumWater Utilities

Coaling Water Authority sewer connection

An agreement spelling out the Coaling Water Authority's use of Tuscaloosa's sewer system. It affects how regional sewer service is shared and paid for.

2 mentionsLast discussed Jul 28, 2026
MediumWater Utilities

Water Distribution & Meter Shop Improvements

The city is spending $62,775 on design for a new 3,600-square-foot water distribution warehouse and meter shop upgrades, drawing on the $8.1 million Hopkins fund from the sale of the old Hopkins building.

2 mentionsLast discussed Jul 28, 2026
HighWater Utilities

Hilliard N. Fletcher WRRF upgrades contract

The council was set to tentatively award a $5.6 million contract to Mark Johnson Construction for switchgear and generator upgrades at the city's wastewater treatment facility. This infrastructure keeps sewer service reliable as Tuscaloosa grows.

1 mentionLast discussed Jul 21, 2026
MediumWater Utilities

2026 Sanitary Sewer Design Manual adoption

The council was scheduled to consider adopting the 2026 edition of the city's sanitary sewer design manual with related code changes. New sewer standards affect how future development and city sewer projects are built.

3 mentionsLast discussed Jul 14, 2026
MediumWater Utilities

Tartan Cove sanitary sewer acceptance

The city accepted the finished sewer lines in the final phase of the Havenridge subdivision off Highway 69 South, completing the neighborhood's public infrastructure.

2 mentionsLast discussed Jul 14, 2026
HighWater Utilities

WRRF switchgear and generator upgrades

The Hilliard N. Fletcher wastewater treatment plant's switchgear and generators date to the 1970s. Replacing them keeps sewage treatment running during power outages.

1 mentionLast discussed Jul 14, 2026
MediumWater Utilities

Water and sewer project fund transfers

Two budget amendments move leftover money from closed water/sewer projects into active ones, including the Taylorville/McFarland booster pump station upgrade.

2 mentionsLast discussed Jun 30, 2026
LowWater Utilities

Fiber network documentation software renewal

The city will spend up to $26,500 to keep Vetro software, which maps every fiber strand and splice in the city's network — critical records for maintaining broadband infrastructure.

1 mentionLast discussed Jun 16, 2026
MediumWater Utilities

Lake Tuscaloosa shoreline erosion at TPD facility

The shoreline at the police department's lake patrol facility has been slowly eroding, tilting the building's asphalt approach toward the water. The city will armor it with riprap before a new storage building goes in, at about $30,000 for materials.

1 mentionLast discussed Jun 16, 2026
MediumWater Utilities

Lake patrol shoreline erosion improvements

The city's water and sewer reserve would shift $30,000 to fix shoreline erosion, funded through the lake patrol budget. It's a maintenance issue tied to protecting the lake shoreline.

1 mentionLast discussed Jun 16, 2026
HighWater Utilities

Online water billing portal and customer notifications

The city is upgrading its Tyler Technologies system so water customers can view past bills, pay multiple accounts in one cart, set auto-pay and opt into texts and emails about bills and trash pickup. Once AMI meters are fully deployed, customers will also see hourly usage trends to spot leaks.

1 mentionLast discussed Jun 9, 2026
MediumWater Utilities

Private Lateral Assistance Program contractor change

The city dropped One Call Service of Alabama as its lateral assistance contractor after it failed to respond to the last request. The program continues this year in piecemeal fashion with about $45,000 left, and a new on-call contract is planned next fiscal year.

1 mentionLast discussed Jun 9, 2026
HighWater Utilities

Booster pump station upgrades

The city is modernizing two booster pump stations so the Hillcrest tank can be taken offline for a full rehab without hurting water pressure. It's an electrical and monitoring overhaul with new generators.

2 mentionsLast discussed Jun 2, 2026
MediumWater Utilities

Restricting out-of-region septic and grease hauling

Tanker trucks have been hauling septic waste and restaurant grease from as far as Mobile to dump at Tuscaloosa's plant. New rules limit acceptance to haulers from counties touching Tuscaloosa plus Shelby County.

1 mentionLast discussed Jun 2, 2026
MediumWater Utilities

MLK sewer and WRRF improvements

Engineering contracts for MLK Boulevard sewer improvements and wastewater treatment lagoon upgrades were on the agenda — the unglamorous work that keeps sewers functioning.

1 mentionLast discussed May 19, 2026
HighWater Utilities

Lake Nicol spillway modifications

An evaluation of the Lake Nicol dam is complete, and the city is moving ahead with spillway modifications to control water levels, with a full dam rehab expected in the next bond cycle around 2027-28.

1 mentionLast discussed May 12, 2026
MediumWater Utilities

Timberlane drainage project

A tentative $98,680.50 contract with Cornerstone Civil Contractors was scheduled to address drainage problems in the Timberlane area.

2 mentionsLast discussed May 12, 2026
MediumWater Utilities

Drainage improvement projects

Several drainage-related items were scheduled: a change order on the waterfall roadway drainage project, an engineering contract for 10th Avenue at 19th Street, and Lincoln Park drainage improvements. Flooding and stormwater concerns in these areas would be addressed if approved.

2 mentionsLast discussed May 5, 2026