Summary
The council was scheduled to tentatively award a roughly $1.6 million contract to REV Constructions, Inc. to replace the Lift Station 22 force main — key sewer infrastructure. No record shows whether the award was made.
At a glance
- Total mentions
- 4
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 6, 2026.
Impact analysis
A $1,614,908.00 construction contract was on the table.
Residents served by Lift Station 22 would benefit from upgraded sewer capacity.
Mentions & discussions (4)
Public Projects Committee - Oct 6, 2026
The city was considering a change order for valve replacements at Lift Stations 40 and 41 and a three-year chemical treatment contract for four lift stations. Keeping lift stations functional prevents sewer backups and overflows in neighborhoods.
City Council - Jun 2, 2026
A $418,476 contract amendment with Duncan Coker Associates for the Lift Station 22 Force Main replacement and wastewater characterization project was on the agenda — a significant sewer system investment.
Public Projects Committee - May 19, 2026
A $41,373 engineering contract amendment for sewer work that keeps the Lift Station 22 force main project on track for a summer construction start.
City Council - May 5, 2026
The council was scheduled to tentatively award a roughly $1.6 million contract to REV Constructions, Inc. to replace the Lift Station 22 force main — key sewer infrastructure. No record shows whether the award was made.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Tuscaloosa
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.