Summary
The city is modernizing two booster pump stations so the Hillcrest tank can be taken offline for a full rehab without hurting water pressure. It's an electrical and monitoring overhaul with new generators.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jun 2, 2026.
Impact analysis
$176,420 for engineering, funded by water/sewer fees, RFFI and the 2022B bond; construction comes later.
Residents in the Hillcrest pressure zone get reliable water service during and after the tank rehab.
Mentions & discussions (2)
Public Projects Committee - Jun 2, 2026
The city is modernizing two booster pump stations so the Hillcrest tank can be taken offline for a full rehab without hurting water pressure. It's an electrical and monitoring overhaul with new generators.
City Council - Mar 10, 2026
The council was set to tentatively award a $1.78 million contract to Mark Johnson Construction for RAS pumping improvements at the Hilliard N. Fletcher wastewater treatment facility.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Tuscaloosa
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.