WRRF switchgear and generator upgrades

Tuscaloosa

Summary

The Hilliard N. Fletcher wastewater treatment plant's switchgear and generators date to the 1970s. Replacing them keeps sewage treatment running during power outages.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jul 14, 2026.

Impact analysis

💰Financial impact

Costs $5,643,449, paid with an SRF loan and 2025B bond — not out of the general fund.

✅Who benefits

Every resident who flushes — reliable wastewater treatment even during storms and outages.