The Hilliard N. Fletcher wastewater treatment plant's switchgear and generators date to the 1970s. Replacing them keeps sewage treatment running during power outages.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 14, 2026.
Impact analysis
Costs $5,643,449, paid with an SRF loan and 2025B bond — not out of the general fund.
Every resident who flushes — reliable wastewater treatment even during storms and outages.