Copeland Square Sanitary Sewer Improvements change order

Tuscaloosa

Summary

The Copeland Square sewer project wrapped up, but crews hit an unexpected storm pipe conflict that added $36,615 and new junction boxes. Final cost: $796,236.

At a glance

Total mentions
1
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Oct 27, 2026.

Impact analysis

💰Financial impact

Adds $36,615 to the contract, covered within the existing project budget.

✅Who benefits

Residents in the 23rd/24th Street area get a modernized sewer line.