Summary
The Hilliard N. Fletcher plant rehab got 120 more days at no extra cost so the biological treatment process in two digesters can stabilize before the third digester is rehabilitated.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 27, 2026.
Impact analysis
No additional cost — time extension only.
Everyone on the city's sewer system benefits from reliable wastewater treatment.