Digester rehabilitation schedule extension
The Hilliard N. Fletcher plant rehab got 120 more days at no extra cost so the biological treatment process in two digesters can stabilize before the third digester is rehabilitated.
Copeland Square Sanitary Sewer Improvements change order
The Copeland Square sewer project wrapped up, but crews hit an unexpected storm pipe conflict that added $36,615 and new junction boxes. Final cost: $796,236.
Nucor Sewer Line cleaning and assessment
Suncoast Infrastructure got the tentative $161,725 contract to clean and assess the Nucor sewer line — routine sanitary sewer maintenance.
2026 Sanitary Sewer Design Manual adoption
A $161,725 contract with Sun Coast Infrastructure for sewer line cleaning plus a water/sewer reserve fund budget amendment keep maintenance moving on core utilities.
SPX Aids to Navigation equipment contract
The airport tower, which currently has no radar, will get ADS-B technology letting controllers track aircraft electronically. Costs are split with the airport's FBO, and federal reimbursement is possible.
WRRF check valve installation
A small but critical repair: a new check valve at the raw sewage pump station keeps sewage flowing the right way at the treatment plant.
Water and Sewer Fund budget revision no. 1
A $154,657 budget revision moves funding for a new water and sewer operations position into contingency instead.
Water and Sewer Fund budget revision no. 1
Amendment No. 5 to the fiscal year 2026 water and sewer reserve for future improvements fund was slated for action — this fund pays for utility system upgrades customers ultimately fund through rates.