Bowers Park Pickleball Courts change order
A change order would trim $79,432.32 from the pickleball court construction contract and push the schedule out 39 days. Residents following the park project would see the cost and timeline shift.
PARA executive director selection
Councilor Eatmon wants the city to have a seat on the committee hiring PARA's next executive director, since the city is a major funder. A resolution may come next week.
Saban Center contract amendments
Three change orders on the Saban Center construction project were on the agenda, adding a combined $3.8 million to the project, plus a $246,480 equipment purchase and an amended exhibits contract bringing that total to $18.7 million.
Honorary designation of Alberta Park as Kip Tyner Plaza
The city was asked to give Alberta Park an honorary name honoring Kip Tyner. Honorary designations don't change the official park name but add recognition.
McDonald Hughes building lighting upgrade
Exterior lights at the McDonald Hughes building will be brought up to LED standards using leftover savings from an under-budget ballpark lighting bid — no new money needed.
Northern Riverwalk Phase II land acquisition
The city is buying land along the north side of the river to extend the Riverwalk — 10.14 acres for up to $515,000, plus a half-acre purchase and an 8-acre donation. This locks in the route for the next phase of the trail and park space.
District 3 Academy Drive benches
The city plans to install benches on lots it bought on Academy Drive, spending $10,000 from the District 3 Improvements Fund. This is a neighborhood improvement for that district.
Amphitheater booking strategy and breakeven philosophy
Mayor Maddox defended the amphitheater's breakeven-not-profit philosophy, saying a profit-first approach would exclude R&B, hip-hop, and community events. The new DWP deal allows four-wall shows where promoters take the risk — a recent low-drawing show still cleared about $20,000 profit.
Chief Tuskaloosa sculpture funding
The Tourism and Sports Commission offered $150,000 toward the Chief Tuskaloosa sculpture, and the city needs to accept the donation and budget it. It's a public art project boosting the city's identity and tourism appeal.
Gym expansion at Richard A. Curry Jr. Complex
A small $14,995 project will expand the gym and weight room at the Richard A. Curry Jr. Complex, adding space and new flooring for recreation users.
Jaycee Park picnic table improvements
Three contracts totaling about $29,100 would pour concrete pads, replace awning roofs, and add metal framing for new roofs over the picnic tables at Jaycee Park. It's a modest park upgrade that keeps a neighborhood gathering spot in good shape.
Riverwalk security, communications, and lighting upgrades
Small thermoplastic markers will help Riverwalk users near Parker Hall stay on the path and find their way to the western and southern riverwalk segments.
Tuscaloosa Tennis Center agreement and liquor license
PARA was set to receive a permissive use agreement for the Tuscaloosa Tennis Center, along with a special liquor license for events at the facility.
Patent Lake condemnation for public park
The council was scheduled to amend an earlier resolution authorizing condemnation proceedings for the Patton Lake Park Project, moving the park project forward.
Patton Lake Park condemnation amendment
The council was scheduled to amend an earlier resolution authorizing condemnation proceedings for the Patton Lake Park Project, moving the park project forward.
McDonald Hughes baseball field lighting
The council was poised to commit up to $500,000 to light upgrades at the McDonald Hughes baseball field plus a $423,353 special appropriation to PARA — a real investment in neighborhood recreation.
Freeman Park & Pool improvements
Two separate budget revisions would shut down leftover balances from the Benjamin Barnes YMCA and Burrell Odom Park projects and roll that money — about $1.55 million combined — into Freeman Park & Pool improvements.
Jaycee Park grading and drainage
Funding from the new Jaycee Park pavilion budget goes toward underground storm drainage and two extra eight-foot sidewalks at the park.
PARA equipment funding
About $423,000 for playground equipment at Palmore Park, equipment at Ol' Colony, and the city's share of general PARA operational gear.
Tuscaloosa Rivermarket audio, visual, and lighting upgrade
A $377,050.02 contract with ESB Group, Inc. was scheduled for consideration to upgrade the Rivermarket's audio, visual, and lighting systems.
Tuscaloosa Metro Animal Shelter
A tentative $256,200 contract award to N.C. Morgan Construction Co., Inc. was on the agenda to re-roof the animal shelter and add a canopy.
River Market lighting and AV upgrades
The River Market's original lights and screens are malfunctioning, risking the city's image with high-profile events. Upgrades were approved as a need, not a want.
District 1 community disbursements
District 1 improvement funds were slated for two local organizations: $1,500 to the Benjamin Barnes YMCA and $1,000 to Elevate West Alabama.
University Boulevard Landscaping Improvements
A $44,400 design-through-construction contract with TTL, Inc. for sprucing up University Boulevard.
Jerry Belk Center expansion
A tentative $8.63 million construction award to J.T. Harrison Construction would expand the Jerry Belk Center — a major investment in a community facility.
District 4 library disbursement
A $5,000 disbursement from District 4 improvement funds to the Tuscaloosa Public Library was scheduled for action.