Saban Center contract amendments

Tuscaloosa

Summary

Three change orders on the Saban Center construction project were on the agenda, adding a combined $3.8 million to the project, plus a $246,480 equipment purchase and an amended exhibits contract bringing that total to $18.7 million.

At a glance

Total mentions
5
Last 30 days
2

Discussed at 2 meetings in the last 60 days; most recently Oct 20, 2026.

Impact analysis

💰Financial impact

The three change orders alone would add $3,810,740 to the Saban Center project.

✅Who benefits

Residents who will use the Saban Center arts and education facility once complete.

⚠️Who could be affected

Taxpayers bear the added project cost through city funds.

Mentions & discussions (5)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Tuscaloosa

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.