Summary
A tentative $256,200 contract award to N.C. Morgan Construction Co., Inc. was on the agenda to re-roof the animal shelter and add a canopy.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Jun 2, 2026.
Impact analysis
The project totals $256,200.00.
The animal shelter, its animals, staff, and visitors benefit from facility improvements.
Mentions & discussions (3)
Finance Committee - Jun 2, 2026
The shelter's Advisory Committee could spend up to $100,000 this fiscal year on repairs and improvements without going back to the three governments. Tuscaloosa's share of the $20,000 bump is $8,800.
City Council - Jun 2, 2026
A tentative $256,200 contract award to N.C. Morgan Construction Co., Inc. was on the agenda to re-roof the animal shelter and add a canopy.
Public Projects Committee - May 19, 2026
The committee was scheduled to award the construction bid for the Metro Animal Shelter to N.C. Morgan Construction Company — a key step toward building the new shelter facility.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Tuscaloosa
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.