Street vacation on 31st Street East
A request to vacate 0.49 acres of the 31st Street East right-of-way abutting Princeton Place in District 6. Vacating surplus right-of-way typically turns public street land over to adjoining property owners.
Highway 69 and US-82 ALDOT agreements
The city wants to budget $270,308 for utility relocation work tied to the Highway 69/Skyland Boulevard intersection project, reimbursed by ALDOT grants. It's a step in a major intersection improvement on the city's south side.
River District Parking Lot Improvements
A $339,000 engineering services contract with TTL, Inc. was on the agenda for River District parking lot improvements — early design work for downtown-adjacent parking.
Subdivision regulation updates (Article IV standards)
The commission was set to review updates to the city's Subdivision Standards and Guidelines — the rules that govern how new neighborhoods are laid out, from streets to lots. Any changes here affect how future development across Tuscaloosa gets platted and built.
Knoll Road street vacation for University Boulevard East project
Construction of the University Boulevard East Improvements project left a portion of Knoll Road unnecessary, and the city was asked to formally vacate it. Road vacations transfer the right-of-way and resolve ownership questions for adjacent property.
Skyland Boulevard streetscape grant
The city was slated to accept an $800,000 state TAP grant for streetscape improvements along Skyland Boulevard (US-11), requiring a $200,000 local match. This affects drivers and businesses along a major south-side corridor.
Downtown lighting and crosswalks
First-ever direct allocation of $325,000 for downtown lighting improvements, plus another $100,000 for the citywide street lighting fund that fills resident requests.
Ash Street sidewalk project
The council was scheduled to consider a $757,144 construction award to GFC Construction plus a $131,923 design contract for Phase 1 of the Ash Street sidewalk. It would add pedestrian infrastructure along Ash Street.
Annual bridge inspections for 30 city bridges
The city must inspect 30 bridges each year under federal rules; a $74,745 contract with John B. Galloway keeps that safety work on schedule through 2026.
Reimbursing cleanup of road spills
Spilled gravel, concrete and debris on city roads have been eating into public works crews' days and budget. The ordinance lets the city bill spilling companies for labor, disposal and fuel costs.
ALDOT road maintenance agreement
A cooperative maintenance agreement with the state for major corridors — McFarland Boulevard, Skyland Boulevard, AL 13, Highway 69 and I-359 — was on the agenda.
Electric scooters in Tuscaloosa
Councilmember Busby was scheduled to present on electric scooters, potentially laying groundwork for how the city would manage or permit shared scooter programs. That could affect sidewalk safety, downtown mobility, and future ordinances.
ALDOT Hwy 69 and Skyland Blvd improvements and utility relocations
ALDOT is widening and regrading Hwy 69 South from Mimosa Park Road to the I-59 overpass; the city must move water and sewer lines, and ALDOT reimburses the full $270,308 cost.
SR-69 intersection utility relocations
The city wants to budget $270,308 for utility relocation work tied to the Highway 69/Skyland Boulevard intersection project, reimbursed by ALDOT grants. It's a step in a major intersection improvement on the city's south side.
Greensboro Avenue streetscape project
A tentative $3.85 million award to GFC Construction was scheduled for the Greensboro Avenue streetscape project, which would upgrade the downtown corridor's appearance and walkability.
Julia Tutwiler Access improvements
After ALDOT's Woolsey Finnell Bridge project, Julia Tutwiler Drive will only get an off-ramp from McFarland Boulevard — no exit back on. A $128,115 amendment keeps the design moving under ATRIP-II requirements.
Rainbow Drive culvert replacement
The council was set to tentatively award a $194,596 contract to Southeastern Sealcoating to replace the culvert at 36th Avenue East and Rainbow Drive — a drainage fix for that corridor.