Cypress Creek Phase III drainage stabilization

Tuscaloosa

Summary

An $863,250 engineering contract to stabilize eroding creek banks, protect utilities, and fix culverts along a mile-long stretch south of Skyland Boulevard. Design will take at least a year with complex permitting.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Apr 7, 2026.

Impact analysis

💰Financial impact

$863,250 for engineering services, part of a larger Noah's Ark program with a future $40+ million bond planned.

✅Who benefits

Property owners and infrastructure along the Cypress Creek drainage area get protection from erosion and flooding.